Around The Homefront
|
The garden pond built into the deck is in need of redevelopment and replacement. This project will involve:
The project will proceed as time and weather allow. Images will display the project from start to finish.
PHASE ONE
PHASE TWO
PHASE THREE
As it was a few years ago. Now in need of upgrade and repair.
|
The demolition begins.
|
Trim is removed now and waterfall feature is being taken down.
|
Closer waterfall feature look.
|
The cavity remaining. I used to have large, biological filters in here in the past.
|
The ponds water level is down.
|
I remove the existing plants.
|
These will probably die before I finish the project. I'll have to start anew.
|
Another angle on the demolition.
|
Decking stripped from structure.
|
White trim shows where new pond walls will be.
|
Another view from waterfall area.
|
And another look. New pond will be L-shaped.
|
Water removed. There are two layers of liner with carpet between the two. This is layer number one.
|
Layer # one removed and carpet cut and removed.
|
Layer number two (old, original) liner.
|
Carpet padding exposed after liner removed. Many roots.
|
Most of padding removed and waterfall structure partly dismantled.
|
Shot of all the roots.
|
Ready for new framework and dirt removal.
|
The digging now begins.
|
It will take awhile. There are thousands of roots to break free first.
|
I've cut the beams to size. Need to add new cross member for new side.
|
This is one of two piles of junk from the bottom.
|
It's likely to take me a week to dig out all I need to remove. This phase could be a boring picture session.
|
The digging produced a pile of padding and roots.
|
But I finally started to make some headway.
|
Stones, roots, hard packed dirt. All in a day's work.
|
Had to remove a small tree that was in the way but also not doing well. More firewood for Geof and Belinda.
|
As always, Rocks...Rocks.
|
And Rocks and Rocks.
|
Framing in place now. Leveled and ready...if I can get the dirt out.
|
Framing near the new waterfall area.
|
After a few days of delay for weather and other priorities, I finally got back to working on the roots removal. Here's one root to be removed...
|
And here's the 'AFTER' with it gone.
|
Here's the next root for removal...
|
And the 'AFTER' with it gone.
|
Roots are HARD WORK and take time and perseverence when done by hand.
|
And it seems every one of them is wrapped around a rock somehow. I've been tossing them under the deck...
|
And a few on the deck for use elsewhere. Two more root clusters to remove and I should be ready to complete the digging.
|
I hit rocks last time so I had to run to the store for a properly sized bit and then sharpen the chainsaw.
|
Also had to get a new handle for the sledge and install it. ![]() |
Took a short look at the Crossvine now beginning to bloom. ![]() |
Then at the first of two roots for today's removal effort. ![]() |
And I removed it!
|
This is the second of the two roots.
|
And I removed it also!
|
On to the large rock in my way with some serious digging in progress now that the roots are gone. ![]() |
I did get quite a pile of them. After all, the pond sits in a grove (copse) of Live Oaks and a couple Hackberry trees. ![]() |
But one more day's digs and I should be ready for Phase Three - the liner installation. ![]() |
With the digging done I move on to the sides and liner installation.
|
I used Hardy cement based paneling. It is impervious to water, strong, and easy to handle.
|
These are merely four views of the sides installed. I will install carpet as a bottom base and cushion for the liner. It protects the liner from punctures from rocks or roots.
|
The notches you see in all these pictures are to allow room in the sides for large rocks I didn't want to remove.
|
The first layer of carpet for the base is in place. This carpet comes from our master bath...almost 30 years old.
|
The carpet keeps the roots and rocks from damaging the liner.
|
I will install a double layer of carpet base. This is the carpet from the room over the kitchen we will no longer need. It comes from the early 70s shag era.
|
It is now in place and the edges are smoothed.
|
I am ready to install the liner next. Then the circulation system, waterfalls, trim.
|
The new liner spread on the garage floor.
|
Fitting the liner to the pond cavity.
|
The other view.
|
The liner is cut to fit and the corner patched. When dried for 24 hours, I can proceed.
|
Added more patching material for a safety margin. Will begin filling pond with water and working on waterfalls next.
|
Electrical for pond filter and pump in place.
|
Makeshift junction box..it works!
|
Adding 200 gallons of water to test for leaks in the patches. You can see new waterfalls device in foreground.
|
Filled pond after setting up pump and skimmer and hose to waterfall. Started waterfall and checked for leakes.
|
Waterfall will be surrounded by plants and other things.
|
Filtering system beginning to do its thing.
|
Water beginning to look pretty clean.
|
And we are beginning to see the end of the project - finally!
|
New, wider trim is laid out.
|
Old decking, upsidedown and recut is in place ready for screw down. Finish waterfall, plants on tiers and in pond, fish introduction, predator control and water control mechanisms to go.
|